Tan Thuan 75MW Offshore Windfarm – Cable Laying Project
The project belongs to the list of wind power projects expected to develop in Ca Mau province in the period from 2020 to 2035.
The project is proposed to have an installed capacity of 75MW, consisting of 18 sets of Siemens Gamesa wind turbines.
Below is the overall summary of the Project.
Project name | Tan Thuan 75MW Offshore Wind Farm Project in Ca Mau Province, Vietnam |
Location | Tan Thuan Commune, Dam Doi District, Ca Mau |
Project Owner | Ca Mau Investment Renewable Power Joint Stock Company (CMC) |
EPC Contractor | PECC2 |
Foundation type | PHC |
Turbine Model | Gamesa Siemens SG5.0 |
Cable Installation Type | Subsea Cables |
Scope of Work | Transportation and Installation of 28km of Subsea Cables |
Installation Schedule | July to October 2021 |